Approximately two (2) weeks prior to scheduled commencement of roofing installation and associated work, a meeting is held at the project site with Armorseal, Architect/Owner, GAFMC representative and any other persons directly concerned with the performance of the work.
A. Tour roofing substrate to inspect substrate, penetrations and and other preparatory work to be performed.
B. Review TOPCOAT Roofing System requirements and specifications (GAFMC Specifications, Detail Drawings and other contract documents).
C. Review required submittals, both completed and yet to be completed.
D. Review final construction schedule related to roofing work, and verify availability of materials, Armorseal's personnel, equipment and facilities needed to consistently make progress and avoid delays.
E. Review required inspection(s), testing, certifying and material usage accounting procedures.
F. Review weather and forecasted weather conditions, as well as procedures for coping with unfavorable conditions including possibility of temporary roofing work.
|